| |
Hindsight
Is 20/20
Managing
the Closeout Process
As
a construction job draws to a close, a
contractor’s interest can be diverted
elsewhere. After all, there’s other
work to be done, and supervisors are needed
on other sites.
But
the last stages of a job require management
attention, too. Most importantly, when
a job ends, a construction company should
study its own performance and produce
a closed-job report. Such a report can
establish a formal end to a contract and
provide the contractor with valuable lessons
going forward.
How Profitable Was It - and Why?
A
closed-job report gives you the opportunity
to look back on a percentage-of-completion
job to find out how profitable it was
and why. By knowing the “why,”
you can develop more precise and accurate
bids on future jobs and, over time, focus
on more profitable contracts.
Among
the functions a closed-job report can
perform are these:
- Declare
the job complete. Closeout
marks the end of a contractual relationship
between contractor and owner. When an
understanding is in place between site
supervisors and accounting personnel
that no more work will be done on a
job, it’s reasonable to declare
it over.
But
processes must also be in place to
modify the report for post-job requirements.
Warranty work, for example, can come
up long after a job is complete. Various
accounting software systems let contractors
include warranty-work costs in a completed
job, or accumulate such costs in a
separate account.
- Account
for all change orders. Contractors
should be satisfied that the costs and
billings for all change orders have
been added to those of the job itself.
This may involve choices: When should
orders be recorded? Should all revenue
be recorded, or just revenue up to the
cost of the order?
- Account
for retainage. Has retainage
been billed and recorded? Different
techniques are used to track billed
and unbilled retainages, but the process
must be consistent to ensure that the
accounting for such transactions is
correct. And closing a job means following
up on your billings, too. Have you been
paid?
- Open
a window on profit fade. Profit
fade occurs when the gross profit percentage
is reasonable or even high in the early
stages of the job, but becomes lower
and lower as time goes on due to revisions
in estimates of job costs.
Contractors
can analyze profit fade on the basis
of completed closed-job reports by
sorting jobs according to estimator,
project manager, job supervisor, etc.
If trends appear, they can be factored
into the bidding process.
- Include
post-completion job audits to review
budget variances and overruns. Actual
figures collected over several jobs
will help put future cost estimates
and bids on firmer footing.
Point
of Substantial Completion Is Critical
It’s
also critical to determine substantial
completion, because that calculation dictates
when profit is recognized.
Generally,
substantial completion should be declared
when remaining costs and risks are insignificant.
A consistent approach is important in
order to avoid the temptation to recognize
completion on some contracts earlier than
others. And the method used to determine
substantial completion should be disclosed
in accounting documents.
Detailed
closed-job reports can help your company
bid more effectively. Our firm can help
you put them together.
Porter Keadle Moore, LLP is a founding
member of ProfitCrew, an association of
accountants and business advisors dedicated
to helping construction companies build
profitable businesses. For information,
contactAdam Polakov at apolakov@pkm.com or Arvil Stanford at astanford@pkm.com or visit www.pkm.com. |
|
Compliments
of:
Porter
Keadle Moore, LLP is a founding
member of ProfitCrew™. Our
commitment to client service and
innovation has won us
local and national acclaim and consistently
exceeds industry standards for financial
reporting quality. |
|
|
|